April 15, 2004

Project Schedule

Microsoft Project - Kinkajou Schedule 2004-04-15_1.jpg Microsoft Project - Kinkajou Schedule 2004-04-15_1.jpg
See the full schedule: [PDF]

Attached is the current schedule incorporating the details of the PCB design. There is a conflict in the Gamma Build and P2 PCB availability. (P1 PCB is not intended for Gamma Build). I think we can work around this and still keep the project on schedule:

Ref:
Task 19: Gamma Prototype Build- 4/22 to 5/12
Task 20: Evaluate Gamma Prototype- 5/13 to 5/26
Task 32: Test/Cal P1-4/28 to 4/29
Task 45: Test/Cal P2- 5/18 to 5/20

Recommendation:
-Build Gamma as per schedule using either external driver or P1 PCB either external or best fit inside if possible, for beginning of evaluation
-prior to end of Task 20 retrofit P2 (task 45) and complete "full evaluation"

Other comments on schedule:
-dates in red have been changed from previous schedule, most significant the Production PCB build cycle extended to 30 days to avoid premium costs, to accomplish this we'll have to select and get to vendor early with preliminary design details to get into his queue.

-the projected "delivery date" for units to WE is 9/10, assembly starting 8/17, we should be able to make a partial delivery by the beginning of September.

-Schedules are traked by date located in the footer under file name.

Posted by Peter Fichter at April 15, 2004 02:04 PM